A. Lamp performed asphalt driveway restorations this past week. The contractor also began grading and installing topsoil in preparation for sod.

The contractor has requested, and been granted, permission for an early start on Saturday, September 22nd.  The contractor will start at 8:00 AM to perform grading and installation of topsoil in preparation for sod.

Next week the contractor will perform manhole repairs in the parkways and perform other miscellaneous repairs. 

Next week the contractor is also scheduled to begin installing sod on Thursday.

Friday, September 14, 2012

A. Lamp is scheduled to perform manhole repairs in the parkway next week along with asphalt driveway restorations.

Following manhole repairs and driveway restorations, landscape restoration with sod will commence.

Friday, September 7, 2012

As part of the 2012 Resurfacing Project, Arrow Road Construction completed asphalt paving of Burr Oak Drive and Mickey Lane this week.

The contractor is anticipating to begin sod restoration, asphalt driveway restoration, and general site clean-up in the near future.