Friday, May 25, 2012

A. Lamp Concrete Contractors and their sub-contractor, RJ Underground, have continued to directional drill the new 8-inch water main along Mickey Lane and Burr Oak Drive.  Last week water main was installed along Burr Oak Drive (South and North).  A. Lamp Concrete Contractors performed storm sewer replacements along Burr Oak Drive and Mickey Lane.

Next week RJ Underground will continue to directional drill water main along Burr Oak Drive (East).  A. Lamp Concrete Contractors will work on storm sewer replacements and open cut water main.

Friday, May 18, 2012

A.Lamp Concrete Contractors and their sub-contractor, RJ Underground, have continued to directional drill the new 8-inch water main along Mickey Lane and Burr Oak Drive. Last week water main was installed along Burr Oak Drive (West), Mickey Lane, and Burr Oak Drive (North).

Next week RJ Underground will continue to directional drill water main along Burr Oak Drive (North, East, and South). A. Lamp Concrete Contractors will work on storm sewer replacements and open cut water main.

Friday, May 11, 2012

This week RJ Underground began directional drilling and installing water main on Burr Oak Drive from the intersection of Burr Oak Drive and Mickey Lane to the south.  On Friday, RJ Underground began directional drilling from the intersection of Mickey Lane and Winnetka Road towards the south.  Next week RJ Underground is scheduled to continue directional drilling on Mickey Lane and Burr Oak Drive.

Monday, May 7, 2012

Directional drilling has begun.

Last week A. Lamp Concrete Construction began making small excavations at the location of existing utilities to verify location.  RJ Underground was also onsite, as a subcontractor to A. Lamp, beginning to directionally drill the new water main on Mickey Lane at the intersection of Burr Oak Drive and Mickey Lane.  On Friday, RJ Underground pulled a section of new water main into the ground at the intersection of Burr Oak and Mickey.  Next week RJ Underground is scheduled to continue directional drilling of the new water main on Burr Oak Drive from Mickey Lane to the south.