Friday, September 21, 2012



A. Lamp performed asphalt driveway restorations this past week. The contractor also began grading and installing topsoil in preparation for sod.

The contractor has requested, and been granted, permission for an early start on Saturday, September 22nd.  The contractor will start at 8:00 AM to perform grading and installation of topsoil in preparation for sod.

Next week the contractor will perform manhole repairs in the parkways and perform other miscellaneous repairs. 

Next week the contractor is also scheduled to begin installing sod on Thursday.