Friday, August 10, 2012

A.Lamp Concrete Contractors has completed all of the underground utility improvements along Burr Oak Drive and Mickey Lane.

The contractor has started to remove portions of the existing curb & gutter along the roadway. Next week the contractor will install  new concrete curb & gutter in the affected areas. Residents will be notified prior to concrete work if your driveway access will be restricted.

Following concrete curb & gutter replacement, the contractor will install asphalt patches in all of the gravel trenches.

The entire roadway along Mickey Lane and Burr Oak Drive will be resurfaced as part of the Village’s 2012 resurfacing project. This work is anticipated to be completed in late August or early September.