A.Lamp Concrete Contractors completed the installation of the open cut water main this week, including the pressure test of the new water main along Burr Oak. The contractor will begin disinfecting the new water mains this week and continue next week. The contractor also began the sanitary sewer replacement along Mickey Lane.

Limited work was performed on-site during this past week due to July 4th Holiday and excessive heat.

Next week A. Lamp Concrete Contractors is anticipating to complete the sanitary sewer replacement along Mickey Lane and other sanitary sewer repairs.

Water services are anticipated to begin the week of July 16th. Residents will be notified prior to any disruption in their water service.

All roadway and driveway access will be restored as soon as possible and at the end of each working day.  Thank you in advance for your patience during this process.