Friday, July 27, 2012

A.Lamp Concrete Contractors completed all water services along Mickey Lane this week. All residents along Burr Oak Drive and Mickey Lane are now connected to the new water main.  The contractor has also performed several connections to the existing water mains and disconnections from the old water mains.

There have been numerous water main shut-downs over the past week due to water service connections, connecting the new water main, and disconnecting the old water mains.  Thank you again for your patience and understanding during this process.

Next week the contractor anticipates performing some miscellaneous tasks such as sewer televising, removing old fire hydrants and valves, and site clean-up.

Once all of the underground work is complete, the contractor will begin scheduling and preparing for concrete curb & gutter replacement and trench paving.

The entire roadway along Mickey Lane and Burr Oak Drive will be resurfaced as part of the Village’s 2012 resurfacing project. This work is anticipated to be completed in late August or early September.