Friday, June 22, 2012

A.Lamp Concrete Contractors began open cut water main installation along Mickey Lane and Burr Oak.  Water main testing is anticipated to begin late next week.

We do not anticipate any water shut-downs in the next week.  The first anticipated water shut down will occur when the individual water services are installed. Notification will be given prior to shutting the water off to your residence.  Water services are not scheduled to begin until after the July 4th Holiday.

Although we do not anticipate any water main shut-downs, the possibly always exist for an emergency shut-down.  In these instances, you will be notified as soon as possible.

A. Lamp Concrete Contractors will continue to perform open cut water main installation, sanitary sewer replacement along Mickey Lane, and underground utility repairs during the next week.

All roadway and driveway access will be restored as soon as possible and at the end of each working day.  Thank you in advance for your patience during this process.