Monday, May 7, 2012

Directional drilling has begun.

Last week A. Lamp Concrete Construction began making small excavations at the location of existing utilities to verify location.  RJ Underground was also onsite, as a subcontractor to A. Lamp, beginning to directionally drill the new water main on Mickey Lane at the intersection of Burr Oak Drive and Mickey Lane.  On Friday, RJ Underground pulled a section of new water main into the ground at the intersection of Burr Oak and Mickey.  Next week RJ Underground is scheduled to continue directional drilling of the new water main on Burr Oak Drive from Mickey Lane to the south.