Friday, May 18, 2012

A.Lamp Concrete Contractors and their sub-contractor, RJ Underground, have continued to directional drill the new 8-inch water main along Mickey Lane and Burr Oak Drive. Last week water main was installed along Burr Oak Drive (West), Mickey Lane, and Burr Oak Drive (North).

Next week RJ Underground will continue to directional drill water main along Burr Oak Drive (North, East, and South). A. Lamp Concrete Contractors will work on storm sewer replacements and open cut water main.