Friday, October 5, 2012

Work Completed

The project is now completed with the exception of a few minor repairs to be completed by the contractor.

This is the last blog update that will be provided for this project.

We appreciate you taking the time to read this blog.

We hope this was a valuable resource for you following the progress of work completed and what work was scheduled in the coming weeks.

Thank you again for all of your patience throughout the construction season.

If you have any outstanding issues that you need addressed, please contact the Project Manager, Andrew Mayes, at 847-904-4410.

Monday, October 1, 2012

 

A. Lamp last week completed sod restoration, manholes repairs, and miscellaneous other work in the parkway.

The project is nearly complete. There are only minor items remaining to be completed. 

Thank you again for all of your patience during this construction season.

Friday, September 21, 2012



A. Lamp performed asphalt driveway restorations this past week. The contractor also began grading and installing topsoil in preparation for sod.

The contractor has requested, and been granted, permission for an early start on Saturday, September 22nd.  The contractor will start at 8:00 AM to perform grading and installation of topsoil in preparation for sod.

Next week the contractor will perform manhole repairs in the parkways and perform other miscellaneous repairs. 

Next week the contractor is also scheduled to begin installing sod on Thursday.

Friday, September 14, 2012

A. Lamp is scheduled to perform manhole repairs in the parkway next week along with asphalt driveway restorations.

Following manhole repairs and driveway restorations, landscape restoration with sod will commence.

Friday, September 7, 2012

As part of the 2012 Resurfacing Project, Arrow Road Construction completed asphalt paving of Burr Oak Drive and Mickey Lane this week.

The contractor is anticipating to begin sod restoration, asphalt driveway restoration, and general site clean-up in the near future.

Thank you for all of your patience during this construction process.  

Friday, August 31, 2012

A.Lamp Concrete Contractors completed trench paving on Burr Oak and Mickey Lane this week.   

The entire roadway along Mickey Lane and Burr Oak Drive will be resurfaced as part of the Village’s 2012 resurfacing project. This work is anticipated to be completed next week.

Thank you for all of your patience getting around the neighborhood.

Saturday, August 25, 2012

A.Lamp Concrete Contractors did not perform any work on-site this week.   

The contractor will work on asphalt trench paving next week.

The entire roadway along Mickey Lane and Burr Oak Drive will be resurfaced as part of the Village’s 2012 resurfacing project. This work is anticipated to be completed within the next two weeks.

Thank you for all of your patience getting around the neighborhood.